Project for the construction of 720 stratum 2 homes, commercial premises, parking spaces and storage rooms.
It is distributed in two condominiums: the first is located in lot 5 of the Mirador del Centenario development and includes two buildings with 18 floors and 144 homes each; the second is located in lots 2 and 3 of the Mirador del Centenario development and consists of three buildings with 18 floors and 144 homes each.
Both are gated condominiums and include a minimarket, lounge, gym, sports area and children’s play area.
Condominium 1:
- Zoning permit: 15 May 2015
- Commencement of sales (288 homes): 15 May 2015
- Commercial break-even point, stage 1.a (144 homes): July 2015
- Commercial break-even point, stage 1.b (144 homes): November 2015
- Commencement of work: January 2016
- Expected date of delivery: May 2017
*** Project completed ***
Condominium 2, stage a:
- Commencement of sales (288 homes): January 2016
- Building permit: July 2016
- Commercial break-even point: November 2016
- Commencement of work: October 2016
- Expected date of delivery: September 2019
Condominium 2, stage b:
- Commencement of sales (144 homes): September 2016
- Building permit: July 2016
- Commercial break-even point: November 2016
- Commencement of work: February 2018
- Expected date of delivery: August 2019